Village of Kelliher - Landfill Decommissioning and Reclamation

Kelliher, Saskatchewan

completeSolid Waste ManagementGIS
Federal contribution
$64,513
Federal share40%

of $161.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 30, 2022
202320242025
Built

Approved 3 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Village of Kelliher
Construction start
Sep 15, 2024(actual)
Construction end
Mar 24, 2025(actual)

Against the original forecast

  • Construction start4 months lateforecast May 29, 2024