Village of Kelliher - Landfill Decommissioning and Reclamation
Federal contribution
$64,513
Federal share40%
of $161.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 30, 2022
202320242025
Built
Approved 3 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Village of Kelliher
- Construction start
- Sep 15, 2024(actual)
- Construction end
- Mar 24, 2025(actual)
Against the original forecast
- Construction start4 months lateforecast May 29, 2024
Also in Kelliher
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 61090 in the federal list. How to read these figures.