Back to projects

Sewage Pumping Station Retrofit

Point Leamington, Newfoundland and Labrador

completeWastewaterGIS
Federal contribution
$258,851
Federal share38%

of $680.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 13, 2021
20222023
Built
Program
Green Infrastructure Stream
Ultimate recipient
Town of Point Leamington
Construction start
Nov 15, 2022(actual)
Construction end
Sep 9, 2023(actual)

Against the original forecast

  • Construction start7 months lateforecast May 1, 2022
  • Construction end3 months lateforecast May 30, 2023

Also in Point Leamington