Sewer System Condition and Capacity Assessment

Inuit Community Government of Nain, Newfoundland and Labrador

completeWastewaterGIS
Federal contribution
$53,017
Federal share40%

of $132.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 28, 2022
20222023
Built

Approved 2 months before the announcement.

Program
Green Infrastructure Stream
Construction start
Nov 10, 2022(actual)
Construction end
Jul 13, 2023(actual)

Against the original forecast

  • Construction start7 months lateforecast Apr 1, 2022
  • Construction end3 months lateforecast Mar 31, 2023

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 61147 in the federal list. How to read these figures.