Lift Station upgrades

Embree, Newfoundland and Labrador

completeDrinking WaterGIS
Federal contribution
$322,764
Federal share40%

of $806.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 13, 2021
202220232024
Built
Program
Green Infrastructure Stream
Ultimate recipient
Town of Embree
Construction start
Jun 1, 2022(actual)
Construction end
Aug 20, 2024(actual)

Against the original forecast

  • Construction start4 weeks lateforecast May 1, 2022
  • Construction end7 months lateforecast Jan 11, 2024

Also in Embree

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 61152 in the federal list. How to read these figures.