Main Street North Water Main Replacement - Phase 1

Elliston, Newfoundland and Labrador

completeDrinking WaterGIS
Federal contribution
$179,115
Federal share40%

of $447.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 13, 2021
20222023
Built
Program
Green Infrastructure Stream
Ultimate recipient
Town of Elliston
Construction start
Aug 1, 2023(actual)
Construction end
Nov 21, 2023(actual)

Against the original forecast

  • Construction start3 months lateforecast May 1, 2023
  • Construction end2 weeks earlyforecast Dec 8, 2023

Also in Elliston

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 61164 in the federal list. How to read these figures.