Main Street North Water Main Replacement - Phase 1
Elliston, Newfoundland and Labrador
Federal contribution
$179,115
Federal share40%
of $447.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 13, 2021
20222023
Built
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Elliston
- Construction start
- Aug 1, 2023(actual)
- Construction end
- Nov 21, 2023(actual)
Against the original forecast
- Construction start3 months lateforecast May 1, 2023
- Construction end2 weeks earlyforecast Dec 8, 2023
Also in Elliston
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 61164 in the federal list. How to read these figures.