Long Pond Road Water and Sewer upgrades

Whiteway, Newfoundland and Labrador

completeWastewaterGIS
Federal contribution
$310,080
Federal share39%

of $793.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 13, 2021
20222023
Built
Program
Green Infrastructure Stream
Ultimate recipient
Town of Whiteway
Construction start
Sep 19, 2022(actual)
Construction end
Jul 28, 2023(actual)

Against the original forecast

  • Construction start3 months lateforecast Jun 7, 2022
  • Construction end8 months lateforecast Dec 6, 2022