Water System Improvements

Newman’s Cove, Newfoundland and Labrador

completeDrinking WaterGIS
Federal contribution
$90,683
Federal share40%

of $226.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 13, 2021
20222023
Built
Program
Green Infrastructure Stream
Ultimate recipient
Newman’s Cove
Construction start
Sep 5, 2023(actual)
Construction end
Nov 22, 2023(actual)

Against the original forecast

  • Construction start3 months lateforecast Jun 1, 2023

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 61191 in the federal list. How to read these figures.