New Waterford Community Wellness Centre
Federal contribution
$3.0M
$3,023,000
Federal share45%
of $6.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 24, 2022
2022202320242025
Built
Approved 5 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Province of Nova Scotia
- Construction start
- May 2, 2022(actual)
- Construction end
- Jan 27, 2025(actual)
Against the original forecast
- Construction end5 weeks lateforecast Dec 20, 2024
Also in Cape Breton
- Cape Breton Regional Municipality - Wastewater Treatment Infrastructure$39.2M
- Cape Breton University - Centre for Discovery and Innovation$20.0M
- Eskasoni First Nation Long Term Care Kiknu$19.7M
- Sydney Harbour West Wastewater Collection and Treatment$19.3M
- CBRM - Battery Electric Bus Purchase and Storage and Maintenance Facility - Phase 2$16.7M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 61270 in the federal list. How to read these figures.