RM of LeRoy No. 339, NNE 9 Bridge Replacement

RM of LeRoy No. 339, Saskatchewan

completeHighways and RoadsRNIS
Federal contribution
$2,834
Federal share17%

of $17.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 30, 2022
2023
Built

Approved 5 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
RM of LeRoy No. 339
Construction start
Feb 9, 2022(actual)
Construction end
Jun 16, 2023(actual)

Against the original forecast

  • Construction start18 months earlyforecast Aug 1, 2023
  • Construction end5 months earlyforecast Nov 15, 2023

Also in RM of LeRoy No. 339

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 61376 in the federal list. How to read these figures.