RM of Caron No. 162, 643 Caron Grid Bridge Replacement

RM of Caron No. 162, Saskatchewan

completeHighways and RoadsRNIS
Federal contribution
$31,615
Federal share17%

of $189.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 30, 2022
2023
Built

Approved 5 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
RM of Caron No. 162
Construction start
Jun 1, 2022(actual)
Construction end
Apr 13, 2023(actual)

Against the original forecast

  • Construction end7 weeks earlyforecast May 31, 2023

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 61378 in the federal list. How to read these figures.