Back to projects

Rural Municipality of Connaught No. 457, Keays Bridge Replacement

Connaught No. 457, Saskatchewan

completeHighways and RoadsRNIS
Federal contribution
$71,851
Federal share17%

of $422.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 30, 2022
Built

Approved 4 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
RM of Connaught No. 457
Construction start
Jul 25, 2022(actual)
Construction end
Aug 30, 2022(actual)

Against the original forecast

  • Construction start3 months lateforecast May 1, 2022
  • Construction end4 months earlyforecast Dec 31, 2022

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 61390 in the federal list. How to read these figures.