Rural Municipality of Connaught No. 457, Keays Bridge Replacement
Connaught No. 457, Saskatchewan
Federal contribution
$71,851
Federal share17%
of $422.7K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 30, 2022
Built
Approved 4 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- RM of Connaught No. 457
- Construction start
- Jul 25, 2022(actual)
- Construction end
- Aug 30, 2022(actual)
Against the original forecast
- Construction start3 months lateforecast May 1, 2022
- Construction end4 months earlyforecast Dec 31, 2022
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 61390 in the federal list. How to read these figures.