Brackley Commons Solar

Rural Municipality of Brackley, Prince Edward Island

completeGreen EnergyGIS
Federal contribution
$12,728
Federal share35%

of $36.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 7, 2024
20232024
Built

Approved 2.1 years before the announcement.

Program
Green Infrastructure Stream
Construction start
May 30, 2022(actual)
Construction end
Jul 22, 2022(actual)

Against the original forecast

  • Construction end3 weeks lateforecast Jun 29, 2022

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 61395 in the federal list. How to read these figures.