Anmore - Community Hub
Federal contribution
$1.0M
$1,022,774
Federal share30%
of $3.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 11, 2022
20232024
Built
Approved 2 months before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Village of Anmore
- Construction start
- Jun 7, 2022(actual)
- Construction end
- Mar 31, 2024(actual)
Against the original forecast
- Construction end4 months lateforecast Dec 15, 2023