Columbia Shuswap - Eagle Bay Community Park
Columbia Shuswap, British Columbia
Federal contribution
$191,947
Federal share40%
of $479.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 11, 2022
2022202320242025
Built
Approved 8 months before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Regional District of Columbia-Shuswap
- Construction start
- Jun 1, 2022(actual)
- Construction end
- Jul 25, 2025(actual)
Also in Columbia Shuswap
- Trans-Canada Highway 1: Ford Road to Tappen Valley Road$82.1M
- Trans-Canada Highway 1 Four-Laning - Jumping Creek to Jack MacDonald Snow Shed$45.7M
- Columbia Shuswap - Scotch Creek Water$1.3M
- Purchase of a vehicle for free on-demand, door-to-door transportation service in Electoral Area C of the Columbia Shuswap Regional District (British Columbia)$72.2K
- Columbia Shuswap - Loftus Lake Fen Universal Trail$31.5K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 61413 in the federal list. How to read these figures.