Kimberley Nordic Club Kiosk Upgrade
Federal contribution
$94,634
Federal share40%
of $236.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 11, 2022
20222023202420252026
Built
Approved 2 months before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Kimberley Nordic Club
- Construction start
- Jun 19, 2025(actual)
- Construction end
- Dec 20, 2025(actual)
Against the original forecast
- Construction start2 weeks lateforecast Jun 5, 2025
- Construction end3 weeks lateforecast Nov 30, 2025
Also in Kimberley
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 61428 in the federal list. How to read these figures.