underwayRecreationCCRIS
Federal contribution
$3.9M
$3,900,000
Federal share75%

of $5.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 11, 2022
20222023202420252026
BuiltForecast

Approved 2 months before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Ultimate recipient
Kitselas First Nation
Construction start
Apr 11, 2023(actual)
Construction end
Dec 20, 2025(forecast)

Against the original forecast

  • Construction start4 months lateforecast Dec 5, 2022

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 61431 in the federal list. How to read these figures.