Northern Saskatchewan Airport Automated Weather Observation System (AWOS) Installations

Cumberland House, Saskatchewan

completeRegional And Local AirportsRNIS
Federal contribution
$625,000
Federal share50%

of $1.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 31, 2022
202220232024
Built

Approved 13 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Construction start
Jul 3, 2023(actual)
Construction end
Mar 31, 2024(actual)