Northern Saskatchewan Airport Automated Weather Observation System (AWOS) Installations
Cumberland House, Saskatchewan
Federal contribution
$625,000
Federal share50%
of $1.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 31, 2022
202220232024
Built
Approved 13 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Saskatchewan Ministry of Highways and Infrastructure
- Construction start
- Jul 3, 2023(actual)
- Construction end
- Mar 31, 2024(actual)