Rufus Guinchard Health Centre & Bonne Bay Health Centre Upgrades
Norris Point, Newfoundland and Labrador
Federal contribution
$280,000
Federal share80%
of $350.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 7, 2024
202220232024
Built
Approved 2.6 years before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Government of Newfoundland and Labrador
- Construction start
- Jun 13, 2022(actual)
- Construction end
- Dec 9, 2023(actual)
Against the original forecast
- Construction start2 months lateforecast Apr 1, 2022
- Construction end5 months lateforecast Jun 30, 2023
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 61471 in the federal list. How to read these figures.