Rufus Guinchard Health Centre & Bonne Bay Health Centre Upgrades

Norris Point, Newfoundland and Labrador

completeHealthcare InfrastructureCVRIS
Federal contribution
$280,000
Federal share80%

of $350.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 7, 2024
202220232024
Built

Approved 2.6 years before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Jun 13, 2022(actual)
Construction end
Dec 9, 2023(actual)

Against the original forecast

  • Construction start2 months lateforecast Apr 1, 2022
  • Construction end5 months lateforecast Jun 30, 2023

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 61471 in the federal list. How to read these figures.