K-12 School Building Envelope Upgrades - Avalon/Eastern Region

Bonavista, Newfoundland and Labrador

completeEducation, Training and ChildcareCVRIS
Federal contribution
$3.3M
$3,290,834
Federal share80%

of $4.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 4, 2025
20222023202420252026
Built

Approved 3.5 years before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Jun 20, 2022(actual)
Construction end
Feb 25, 2026(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Jun 1, 2022
  • Construction end5 weeks earlyforecast Mar 31, 2026

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 61472 in the federal list. How to read these figures.