K-12 School Building Envelope Upgrades - Avalon/Eastern Region
Bonavista, Newfoundland and Labrador
Federal contribution
$3.3M
$3,290,834
Federal share80%
of $4.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 4, 2025
20222023202420252026
Built
Approved 3.5 years before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Newfoundland and Labrador English School District
- Construction start
- Jun 20, 2022(actual)
- Construction end
- Feb 25, 2026(actual)
Against the original forecast
- Construction start3 weeks lateforecast Jun 1, 2022
- Construction end5 weeks earlyforecast Mar 31, 2026
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 61472 in the federal list. How to read these figures.