Ashcroft Indian Band - Community Centre
Ashcroft Indian Band, British Columbia
Federal contribution
$3.6M
$3,562,500
Federal share75%
of $4.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 26, 2022
today
20232024202520262027
BuiltForecast
Approved 5 months before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Ashcroft Indian Band
- Construction start
- Oct 1, 2025(actual)
- Construction end
- Apr 15, 2027(forecast)
Against the original forecast
- Construction start6 months lateforecast Apr 15, 2025
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 61486 in the federal list. How to read these figures.