Stz'uminus Long House Renovation and Expansion
Stz'uminus First Nation, British Columbia
Federal contribution
$3.1M
$3,075,000
Federal share75%
of $4.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 11, 2022
2022202320242025
Built
Approved 2 months before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Stz'uminus First Nation
- Construction start
- Jan 20, 2023(actual)
- Construction end
- May 15, 2025(actual)
Against the original forecast
- Construction start7 weeks lateforecast Dec 1, 2022
- Construction end5 months lateforecast Dec 15, 2024