Back to projects

Stz'uminus Long House Renovation and Expansion

Stz'uminus First Nation, British Columbia

completeRecreationCCRIS
Federal contribution
$3.1M
$3,075,000
Federal share75%

of $4.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 11, 2022
2022202320242025
Built

Approved 2 months before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Ultimate recipient
Stz'uminus First Nation
Construction start
Jan 20, 2023(actual)
Construction end
May 15, 2025(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Dec 1, 2022
  • Construction end5 months lateforecast Dec 15, 2024

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 61487 in the federal list. How to read these figures.