Celebration Park
Sunshine Valley, British Columbia
Federal contribution
$125,712
Federal share40%
of $314.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 11, 2022
202320242025
Built
Approved 2 weeks before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- SVC Recreation Society
- Construction start
- Jun 27, 2022(actual)
- Construction end
- Aug 20, 2025(actual)
Against the original forecast
- Construction start6 weeks lateforecast May 15, 2022
- Construction end3 weeks lateforecast Jul 31, 2025
Also in Sunshine Valley
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 61489 in the federal list. How to read these figures.