Celebration Park

Sunshine Valley, British Columbia

completeRecreationCCRIS
Federal contribution
$125,712
Federal share40%

of $314.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 11, 2022
202320242025
Built

Approved 2 weeks before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Ultimate recipient
SVC Recreation Society
Construction start
Jun 27, 2022(actual)
Construction end
Aug 20, 2025(actual)

Against the original forecast

  • Construction start6 weeks lateforecast May 15, 2022
  • Construction end3 weeks lateforecast Jul 31, 2025

Also in Sunshine Valley

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 61489 in the federal list. How to read these figures.