Schedule

Announced and approvedAug 19, 2022
202320242025
Built

Approved 4 months before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Ultimate recipient
Tseshaht First Nation
Construction start
Apr 8, 2024(actual)
Construction end
Aug 12, 2025(actual)

Against the original forecast

  • Construction start2 months lateforecast Jan 24, 2024
  • Construction end6 months lateforecast Feb 7, 2025