Back to projects

Xeni Gwet'in Community Centre

Xeni Gwet'in First Nation, British Columbia

underwayRecreationCCRIS
Federal contribution
$4.2M
$4,166,250
Federal share75%

of $5.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 11, 2022
today
20222023202420252026
BuiltForecast

Approved 2 months before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Ultimate recipient
Xeni Gwet'in First Nation
Construction start
Mar 3, 2025(actual)
Construction end
Sep 30, 2026(forecast)

Against the original forecast

  • Construction start3 months earlyforecast Jun 2, 2025

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 61495 in the federal list. How to read these figures.