Arena Roof and Changeroom
Yunesit'in Government, British Columbia
Federal contribution
$300,000
Federal share75%
of $400.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 11, 2022
today
202220232024202520262027
BuiltForecast
Approved 2 months before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Yunesit'in Government
- Construction start
- Jul 7, 2026(forecast)
- Construction end
- Oct 30, 2026(forecast)