Ventilation Upgrades at Various Health Centres
Botwood, Newfoundland and Labrador
Federal contribution
$800,000
Federal share80%
of $1.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 4, 2025
2022202320242025
Built
Approved 3.2 years before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Government of Newfoundland and Labrador
- Construction start
- Nov 1, 2022(actual)
- Construction end
- Apr 30, 2025(actual)
Against the original forecast
- Construction end11 months earlyforecast Mar 31, 2026
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 61544 in the federal list. How to read these figures.