Ventilation Upgrades at Various Health Centres

Botwood, Newfoundland and Labrador

completeVentilationCVRIS
Federal contribution
$800,000
Federal share80%

of $1.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 4, 2025
2022202320242025
Built

Approved 3.2 years before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Nov 1, 2022(actual)
Construction end
Apr 30, 2025(actual)

Against the original forecast

  • Construction end11 months earlyforecast Mar 31, 2026

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 61544 in the federal list. How to read these figures.