Kimberley - Centre 64 Arts Centre Roof and Truss Upgrades

Kimberley, British Columbia

completeCultureRNIS
Federal contribution
$205,550
Federal share50%

of $411.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 11, 2022
Built

Approved 2 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
City of Kimberley
Construction start
Apr 25, 2022(actual)
Construction end
Oct 31, 2022(actual)