Campbellton - Upgrading of Infrastructure on Adam Street and Dufferin Street
Federal contribution
$736,547
Federal share40%
of $1.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 25, 2022
20222023202420252026
BuiltForecast
Approved 6 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- City of Campbellton
- Construction start
- Jun 5, 2023(actual)
- Construction end
- Jun 1, 2026(forecast)
Also in Campbellton
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 61986 in the federal list. How to read these figures.