St. Theresa Point School Solar
St. Theresa Point First Nation, Manitoba
Federal contribution
$1.5M
$1,541,838
Federal share100%
of $1.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 9, 2022
20222023
Built
Approved 11 months before the announcement.
- Program
- Green and Inclusive Community Buildings Program
- Ultimate recipient
- St. Theresa Point First Nation
- Construction start
- Apr 1, 2022(actual)
- Construction end
- Aug 14, 2023(actual)
Against the original forecast
- Construction start2 weeks earlyforecast Apr 18, 2022
- Construction end13 months lateforecast Jul 18, 2022
Also in St. Theresa Point First Nation