Back to projects

Skidegate Band Council - TLL Yahda Energy Solar Farm

Tlaa Gaa Aawtlaas, Old Massett, British Columbia

completeGreen EnergyGIS
Federal contribution
$3.0M
$3,039,485
Federal share75%

of $4.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 27, 2022
2023202420252026
Built

Approved 7 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Tll Yahda Energy
Construction start
Apr 17, 2023(actual)
Construction end
Dec 5, 2025(actual)

Against the original forecast

  • Construction start2 months lateforecast Feb 1, 2023
  • Construction end5 weeks earlyforecast Jan 12, 2026

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 62091 in the federal list. How to read these figures.