Skidegate Band Council - TLL Yahda Energy Solar Farm
Tlaa Gaa Aawtlaas, Old Massett, British Columbia
Federal contribution
$3.0M
$3,039,485
Federal share75%
of $4.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 27, 2022
2023202420252026
Built
Approved 7 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Tll Yahda Energy
- Construction start
- Apr 17, 2023(actual)
- Construction end
- Dec 5, 2025(actual)
Against the original forecast
- Construction start2 months lateforecast Feb 1, 2023
- Construction end5 weeks earlyforecast Jan 12, 2026
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 62091 in the federal list. How to read these figures.