Back to projects

Rural Green Vehicle Market Study for the Restigouche RSC Territory of New Brunswick

Restigouche County, New Brunswick

completeCapacity BuildingRTSF
Federal contribution
$30,000
Federal share79%

of $38.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 7, 2024
20232024
Built

Approved 23 months before the announcement.

Program
Permanent Public Transit Program
Construction start
Nov 5, 2023(actual)
Construction end
May 30, 2024(actual)

Against the original forecast

  • Construction start22 months lateforecast Jan 10, 2022
  • Construction end24 months lateforecast Jun 10, 2022

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 62108 in the federal list. How to read these figures.