Rural Regional Transportation Model for Southeast Manitoba
Federal contribution
$50,000
Federal share100%
of $50.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 27, 2024
20232024
Built
Approved 2.2 years before the announcement.
- Program
- Permanent Public Transit Program
- Ultimate recipient
- Rural Municipality of Piney
- Construction start
- May 5, 2022(actual)
- Construction end
- Nov 30, 2023(actual)
Against the original forecast
- Construction start4 weeks lateforecast Apr 4, 2022
- Construction end8 months lateforecast Mar 31, 2023
Also in Piney
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 62112 in the federal list. How to read these figures.