Bringing Commuter Public Transit to Rural Kingston, Gananoque and South Frontenac
Federal contribution
$50,000
Federal share100%
of $50.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 18, 2025
202320242025
Built
Approved 2.9 years before the announcement.
- Program
- Permanent Public Transit Program
- Ultimate recipient
- City of Kingston
- Construction start
- Jun 1, 2022(actual)
- Construction end
- Sep 21, 2023(actual)
Against the original forecast
- Construction start4 months lateforecast Feb 1, 2022
- Construction end11 months lateforecast Oct 31, 2022
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 62116 in the federal list. How to read these figures.