Two Hills and Area Community Assisted Transportation Project, Alberta

Myrnam, Alberta

completeCapacity BuildingRTSF
Federal contribution
$11,635
Federal share100%

of $11.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 26, 2024
20232024
Built

Approved 2.2 years before the announcement.

Program
Permanent Public Transit Program
Construction start
Aug 15, 2022(actual)
Construction end
Jun 30, 2023(actual)

Against the original forecast

  • Construction start9 months lateforecast Nov 1, 2021
  • Construction end12 months lateforecast Jun 30, 2022

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 62124 in the federal list. How to read these figures.