Back to projects

Eeyou Mobility phase 2

Baie-James, Quebec

underwayBroadband And ConnectivityRNIS
Federal contribution
$10.0M
$10,048,694
Federal share43%

of $23.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedNov 14, 2023
2023202420252026
BuiltForecast

Approved 20 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
James Bay Eeyou Society
Construction start
Aug 15, 2023(actual)
Construction end
Mar 31, 2026(forecast)

Also in Baie-James