Back to projects

Stratford Community Campus - Site Servicing

Stratford, Prince Edward Island

underwayWastewaterGIS
Federal contribution
$2.6M
$2,644,108
Federal share40%

of $6.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 1, 2022
today
202220232024202520262027
BuiltForecast

Approved 7 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Stratford
Construction start
May 23, 2023(actual)
Construction end
Oct 31, 2026(forecast)

Also in Stratford

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 62332 in the federal list. How to read these figures.