Back to projects

Saint-Antonin sports center and ice rink roof

Saint-Antonin, Quebec

completeRecreationCCRIS
Federal contribution
$1.3M
$1,296,942
Federal share33%

of $3.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 15, 2022
2023202420252026
Built

Approved 3 months before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Construction start
Aug 5, 2024(actual)
Construction end
Feb 10, 2026(actual)

Against the original forecast

  • Construction end7 months lateforecast Jul 18, 2025

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 62408 in the federal list. How to read these figures.