Oliphant Lake Dam Disaster Mitigation

Malahat First Nation, British Columbia

approvedDisaster MitigationDMAF
Federal contribution
$9.5M
$9,504,572
Federal share100%

of $9.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedNov 30, 2022
today
202320242025202620272028
BuiltForecast

Approved 4 months before the announcement.

Program
Disaster Mitigation and Adaptation Fund
Ultimate recipient
Malahat First Nation
Construction start
Jan 1, 2027(forecast)
Construction end
Dec 10, 2027(forecast)