Back to projects

Norton Elementary School - Ventilation Upgrades

Norton, New Brunswick

completeVentilationCVRIS
Federal contribution
$320,000
Federal share80%

of $400.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 7, 2024
20232024
Built

Approved 2.1 years before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Province of New Brunswick
Construction start
Jun 27, 2022(actual)
Construction end
Oct 17, 2022(actual)

Against the original forecast

  • Construction start4 months lateforecast Feb 11, 2022
  • Construction end7 weeks lateforecast Aug 27, 2022

Also in Norton

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 62643 in the federal list. How to read these figures.