Norton Elementary School - Ventilation Upgrades
Federal contribution
$320,000
Federal share80%
of $400.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 7, 2024
20232024
Built
Approved 2.1 years before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Province of New Brunswick
- Construction start
- Jun 27, 2022(actual)
- Construction end
- Oct 17, 2022(actual)
Against the original forecast
- Construction start4 months lateforecast Feb 11, 2022
- Construction end7 weeks lateforecast Aug 27, 2022
Also in Norton