Burton Elementary School - Ventilation Upgrades
Federal contribution
$240,000
Federal share78%
of $308.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 28, 2024
20232024
Built
Approved 2.5 years before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Province of New Brunswick
- Construction start
- Jun 29, 2022(actual)
- Construction end
- May 1, 2023(actual)
Against the original forecast
- Construction start5 months lateforecast Feb 12, 2022
- Construction end8 months lateforecast Aug 26, 2022
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 62645 in the federal list. How to read these figures.