École Blanche-Bourgeois - Ventilation Upgrades

Cocagne, New Brunswick

completeVentilationCVRIS
Federal contribution
$360,000
Federal share59%

of $606.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 7, 2024
20232024
Built

Approved 2.1 years before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Province of New Brunswick
Construction start
Jun 27, 2022(actual)
Construction end
Jan 20, 2023(actual)

Against the original forecast

  • Construction start4 months lateforecast Feb 12, 2022
  • Construction end4 weeks lateforecast Dec 20, 2022