Development of play modules for children
Sainte-Anne-de-la-Pérade, Quebec
Federal contribution
$25,967
Federal share33%
of $77.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 10, 2022
2023
Built
Approved 2 months before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Municipality of Sainte-Anne-de-la-Pérade
- Construction start
- Sep 13, 2023(actual)
- Construction end
- Oct 31, 2023(actual)
Against the original forecast
- Construction start3 months lateforecast Jun 1, 2023
- Construction end5 months earlyforecast Mar 30, 2024
Also in Sainte-Anne-de-la-Pérade
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 62710 in the federal list. How to read these figures.