Back to projects

South St. Clements Activity Centre

St. Clements, Manitoba

underwayRecreationCCRIS
Federal contribution
$2.5M
$2,454,778
Federal share40%

of $6.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 31, 2022
today
2023202420252026
BuiltForecast

Approved 5 months before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Construction start
Mar 26, 2024(actual)
Construction end
Aug 31, 2026(forecast)

Against the original forecast

  • Construction start4 weeks lateforecast Mar 1, 2024

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 62749 in the federal list. How to read these figures.