School Ventilation Upgrades

Alberton, Prince Edward Island

completeVentilationCVRIS
Federal contribution
$2.5M
$2,506,040
Federal share80%

of $3.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 8, 2025
20222023202420252026
Built

Approved 2.9 years before the announcement.

Program
COVID-19 Resilience Stream
Construction start
May 16, 2022(actual)
Construction end
Mar 17, 2026(actual)

Against the original forecast

  • Construction end2 months lateforecast Jan 15, 2026

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 62758 in the federal list. How to read these figures.