Back to projects

Rehabilitation of the Armstrong Water Treatment Plant

Undefined, Ontario

underwayDrinking WaterGIS
Federal contribution
$1.9M
$1,906,678
Federal share40%

of $4.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 14, 2022
today
202220232024202520262027
BuiltForecast

Approved 6 weeks before the announcement.

Program
Green Infrastructure Stream
Construction start
Apr 28, 2025(actual)
Construction end
Jun 30, 2027(forecast)

Also in Undefined