Replacement of Ouse Street North, Kerr Street, Norton Street and Mohawk Street Watermains

Haldimand, Ontario

completeDrinking WaterGIS
Federal contribution
$673,200
Federal share40%

of $1.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 14, 2022
2023
Built

Approved 2 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
County of Haldimand
Construction start
Aug 3, 2022(actual)
Construction end
Jun 30, 2023(actual)

Also in Haldimand

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 62777 in the federal list. How to read these figures.