White River Water Treatment Plant Rehabilitation

White River, Ontario

underwayDrinking WaterGIS
Federal contribution
$648,500
Federal share40%

of $1.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 14, 2022
today
202220232024202520262027
BuiltForecast

Approved 6 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Township of White River
Construction start
Sep 1, 2022(actual)
Construction end
Mar 31, 2027(forecast)

Also in White River

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 62792 in the federal list. How to read these figures.