Main Street and Cedar Point Road Watermain Replacement

Wabigoon Lake Ojibway Nation, Ontario

completeDrinking WaterGIS
Federal contribution
$3.5M
$3,454,313
Federal share75%

of $4.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 14, 2022
2023202420252026
Built

Approved 6 weeks before the announcement.

Program
Green Infrastructure Stream
Construction start
Feb 4, 2025(actual)
Construction end
Nov 11, 2025(actual)

Against the original forecast

  • Construction end10 months earlyforecast Aug 29, 2026