Arnprior Water Filtration Plant Clearwell Replacement

Arnprior, Ontario

underwayDrinking WaterGIS
Federal contribution
$1.0M
$1,000,000
Federal share40%

of $2.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 14, 2022
today
202220232024202520262027
BuiltForecast

Approved 6 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Arnprior
Construction start
Apr 1, 2026(actual)
Construction end
Mar 31, 2027(forecast)

Also in Arnprior