Bennet Street and Boundary Road Watermain Replacement and Taylor Bridge Watermain Suspension

Pembroke, Ontario

completeDrinking WaterGIS
Federal contribution
$1.9M
$1,909,000
Federal share40%

of $4.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 14, 2022
202320242025
Built

Approved 3 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
City of Pembroke
Construction start
Sep 16, 2022(actual)
Construction end
Mar 26, 2025(actual)

Against the original forecast

  • Construction start15 months earlyforecast Dec 22, 2023