Bennet Street and Boundary Road Watermain Replacement and Taylor Bridge Watermain Suspension
Federal contribution
$1.9M
$1,909,000
Federal share40%
of $4.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 14, 2022
202320242025
Built
Approved 3 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- City of Pembroke
- Construction start
- Sep 16, 2022(actual)
- Construction end
- Mar 26, 2025(actual)
Against the original forecast
- Construction start15 months earlyforecast Dec 22, 2023
Also in Pembroke
- HVAC System UV Treatment; HVAC Duct Sealing; Ventilation$2.2M
- Reconstruction of a Section of Pembroke Street West$2.0M
- HVAC Upgrades; Portable Replacement; Installation of Bottle Filling Stations$1.5M
- Algonquin Trail North Active Transportation Enhancements$1.5M
- HVAC Upgrades; Portable Replacement; Installation of Bottle Filling Stations$1.2M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 62953 in the federal list. How to read these figures.